Dilapidation Reports Before a Melbourne Demolition: When You Need One
A demolition shakes the ground, moves heavy machines along a driveway and puts trucks on the nature strip for days at a time. Most of the time the houses next door and the footpath out front come through untouched. Occasionally a crack appears in a neighbour's render, a paver lifts or a section of kerb breaks, and the question becomes whether it was already there. A dilapidation report is how you answer that question before it is asked.
This guide explains what a dilapidation report is, when one is worth getting before a Melbourne demolition, what it should include, and how it fits into the rest of the program.
What a dilapidation report is
A dilapidation report, sometimes called a condition report or pre-construction survey, is a dated record of the condition of a property before nearby work begins. It usually includes a written description and a large set of photographs, often with a measuring scale in shot, showing existing cracks, stains, uneven floors, damaged paving, gaps in fences and anything else that could later be blamed on the job.
Reports can cover neighbouring houses, shared fences and boundary walls, and public assets such as the footpath, kerb, crossover and nature strip. A second inspection after the work finishes lets both sides compare like with like.
When you are likely to need one
Neighbours close to the boundary
On tight inner and middle-ring blocks, such as a Californian bungalow in Coburg or a weatherboard in Footscray, the house next door can be less than a metre from the wall being demolished. A boundary garage, a shared wall or a neighbour's extension built to the fence line makes a report much more worthwhile. Under Victoria's protection work process, where building work may affect an adjoining property, the building surveyor can require protection work and notices to the neighbour. A dilapidation report often sits alongside that process.
Older or fragile neighbouring homes
Period homes with solid brick walls, render and original ceilings can show cracks that have been there for decades. Recording them before demolition starts protects you from being blamed and protects the neighbour if new damage really does occur.
Council assets out front
Many Melbourne councils require an asset protection permit before demolition, and part of that process involves the condition of the footpath, kerb, crossover and nature strip. Some councils inspect themselves. Others expect the owner or builder to supply photos. Either way, a clear record of existing damage can save a dispute about who pays for a cracked footpath at the end of the job.
Development and commercial sites
On a dual occupancy, townhouse or commercial site, the builder, the lender or the developer's insurer may ask for dilapidation reports on adjoining properties as a standard condition.
Who prepares it and when
Dilapidation reports are usually prepared by building consultants, engineers or specialist inspectors. The report should be done before any demolition work begins, including the soft strip and asbestos removal, because those stages can involve vehicles and equipment on site too.
Your neighbour has to agree to an inspection of their property. Most do, especially once it is explained that the report protects them as well. Give them plenty of notice, offer a time that suits, and agree that they will receive a copy. If a neighbour declines, a report can still record what is visible from your side and from the street, and that is better than nothing.
What a good report includes
A useful report has dated photos with clear location references, descriptions of existing defects, notes on the type of construction, and enough detail that someone else could find the same crack again. It should cover the parts of the neighbouring property most likely to be affected, usually the walls and fences closest to the boundary and anything with a path for vibration, such as paving or a garage slab.
It is also worth keeping your own photos and a short video of the street frontage on the morning the machines arrive. It takes ten minutes and adds another dated record.
How it fits with the demolition
A dilapidation report does not replace good demolition practice. Choosing the right machine for the block, pulling walls inward rather than towards a boundary, controlling dust with water and keeping trucks clear of fragile kerbs all reduce the chance of damage in the first place. The report simply makes sure that if a question comes up later, there is a record to answer it.
On our House & Unit Demolition and Strip-Outs & Partial Demolition jobs we plan around neighbouring structures from the first site visit, and we can let you know early whether a dilapidation report is worth commissioning for your block. Our Demolition Permits & Council Approvals service also covers the asset protection side of the paperwork, so the footpath and crossover are recorded properly before work begins.
Across Melbourne
Requirements and expectations vary between councils, from the established streets of the northern suburbs to newer estates in the south-east and larger blocks around Frankston and the Mornington Peninsula. The safest approach is to check with your council and building surveyor, then decide with your contractor whether a report on the neighbouring properties is worthwhile.
Getting started
If you are planning a demolition anywhere across Melbourne and want to understand whether you need a dilapidation report, get in touch. We will look at the block, the neighbours and the street during a free site visit and include clear advice with your quote.
Get the block cleared properly.
Free on-site quotes · Permits and abolishment handled · Melbourne-wide