Demolition for a Dual Occupancy or Townhouse Development in Melbourne

A growing share of the house demolitions we do across Melbourne are not for a family building their dream home. They are for a dual occupancy, a pair of townhouses, or a three or four unit development on a block that used to hold one post-war house. The demolition itself is not radically different, but the context is, and the developers who get it right treat site clearing as the first stage of the build rather than a job to tick off before the builder arrives.

Here is how demolition fits into a multi-unit project, what the builder actually needs from the cleared site, and where projects lose time.

Sequencing with the planning permit

The first question is whether to demolish before or after the planning permit is issued. There is no single right answer, but there are consequences either way.

Demolishing early gives a clean site for the survey and geotechnical investigation, removes the holding costs of an empty house, and avoids the risk of squatters or vandalism in a vacant dwelling. The risk is that the planning application is refused or substantially changed, and you are left with a vacant block and a dwelling you can no longer put back.

Waiting for the permit is safer on the planning side, but it means the house sits for months, and the demolition then sits on the critical path with the builder waiting. In practice many developers demolish once the permit is issued or once it is clearly heading that way, and run the building permit application in parallel.

One thing to be clear on: a planning permit for the development does not itself authorise the demolition. That still needs its own building permit and, in many parts of Melbourne, a Section 29A report and consent from council, which is covered on this site in more detail. Heritage overlays, common in the inner and middle-ring suburbs where multi-unit development is concentrated, can add a planning requirement for demolition itself.

What the builder needs the site to look like

A single-home builder generally wants a clear, level block with the slab and footings gone. A townhouse builder wants the same, and also cares about things that matter more when the new footprint covers most of the site.

The whole footprint needs to be clear, which usually means every outbuilding, every path, the old driveway and crossover, retaining walls that are not being retained, and any underground tanks or pits. A multi-unit build typically covers far more of the block than the old house did, so structures that could have been left on a single-home job have to go.

Old footings, stumps and services need to be removed or properly capped, not just cut off at ground level. A builder who finds an old brick footing where a new strip footing is meant to go will charge for the delay.

Fill and levels matter. If the site needs to be brought to a particular level for the new slab, that is a conversation to have with the builder before we finish, so the demolition and any cut or fill can be coordinated rather than done twice.

Crossovers are a common gap. A multi-unit development often needs a new or relocated crossover, and the old one usually has to be removed and the kerb and nature strip reinstated to council's satisfaction. That is a council permit in its own right.

Services on a multi-unit site

Electricity, gas, water and sewer need to be abolished, not just disconnected, before demolition. On a development site there is a further wrinkle: the new project needs new services, often more than one connection, and the location of the old ones affects where the new ones can go. Early conversation with the builder and the service authorities about what is being abolished and what is being retained saves a lot of trouble. Service abolishment timelines in Melbourne are also long enough that this should be started well before the demolition date.

Neighbours and protection works

Multi-unit builds generally push closer to the boundaries than the house they replace, and demolition on a tight block frequently happens within a metre of a neighbour's fence, garage or house. Where demolition or excavation could affect an adjoining property, protection work notices under the Building Act may be required, and the neighbours need to be dealt with properly. On a development, the relationship with the neighbours lasts for the whole build, so starting it well at the demolition stage is worth the effort.

Asbestos and the developer's duty

The houses that get replaced with townhouses in Melbourne are, overwhelmingly, from the decades when asbestos was everywhere: the 1940s to the 1980s. An asbestos assessment before demolition is not optional on these sites, and the developer as the person commissioning the work carries responsibility for it being done properly. Our asbestos removal and disposal is licensed and documented, and the clearance certificate becomes part of the project record the builder and eventually the purchasers may want to see.

Timeframes on a development site

The demolition itself is a matter of days. What takes time is everything around it: asbestos assessment and removal, service abolishment, permits and consents, protection works if required, and the removal of everything beyond the house. Developers who plan for four to eight weeks from engaging a demolisher to a cleared site rarely get caught out. Those who plan for two do.

Getting the quote right

A demolition quote for a development site should be explicit about the full scope: house, outbuildings, slabs, paths, driveway, crossover, fences, retaining walls, trees to be removed, services, asbestos, and the finished level and condition of the site. Vague quotes cost developers money because the gaps get charged as variations or, worse, become the builder's problem. We quote the whole scope, in writing, after a site visit.

Talk to us early

We clear sites for dual occupancy, townhouse and small unit developments across Melbourne's northern, western, south-eastern and outer eastern suburbs. The best time to involve us is when the planning application goes in, not when the permit comes out, because that is when the sequencing decisions get made.

Get a Free Quote

Get the block cleared properly.

Free on-site quotes · Permits and abolishment handled · Melbourne-wide

Request a Quote
Get in touch