Knockdown-Rebuild Demolition Checklist: What Your Builder Needs From Your Demolisher

On a knockdown-rebuild there are two contracts and one block. The demolition contract ends when the house is gone. The building contract starts when the builder accepts the site. If those two definitions do not match, you pay for the gap in delays, site-cost variations and a second mobilisation.

Most volume and custom builders spell out what they expect at handover somewhere in their documents, often in the site conditions or pre-start section. Get that page early and give it to your demolisher before they quote. Then work through the list below, which covers what builders across Melbourne commonly need and what a good demolition scope should promise in writing.

A block cleared to the builder's spec

Cleared means different things to different people. For a builder it generally means no structure, no rubble, no vegetation that has not been approved to stay, and no buried debris. That includes the house, garage, carport, sheds, fences inside the block, garden walls, paving and any old retaining that is being replaced.

Ask the builder whether dividing fences stay, whether any trees are being retained, and whether they want the front fence out for access. Put the answers in the demolition scope, not in an email thread.

Slab, stumps and footings out

A house coming down to floor level is not a cleared block. Stumps, strip footings, slab edges, old extension slabs and the garage slab all need removing, along with the driveway and paths if the new design does not reuse them. Anything left in the ground is something your builder's engineer did not design for, and it tends to surface during excavation for the new footings, when it is most expensive to deal with. Our guide Concrete Slab and Driveway Removal in Melbourne goes into what that work involves.

Levels your surveyor can set out on

The handover state should be graded close to natural ground level, reasonably even, and free of mounds of spoil. Holes left by footings, stumps, tree roots and any pool should be backfilled in compacted layers rather than simply tipped in.

What a builder does not want is a block scraped well below natural level, or one built up with imported fill that nobody recorded. Both change the site classification assumptions and can affect slab design. If the new home involves a cut-and-fill, talk to your builder about whether that earthwork belongs in the demolition scope while the machines are still on site.

Natural soil left for the soil test

Many builders commission, or re-do, the soil test and site classification after demolition, because the old house hid part of the ground. That test needs natural soil to sample. Keep spoil heaps, crushed concrete and stockpiled rubble off the building envelope, and ask your demolisher to note and photograph anywhere fill has been placed, such as an old pool or a deep backfilled footing. Your geotechnical engineer will want to know where those areas are.

Tree protection still standing

If any tree on the block, on the nature strip or next door is protected, the tree protection fencing installed for demolition usually needs to stay in place for the build. Confirm who owns it at handover, and make sure it has not been moved or flattened by the last truck out. Neighbours, Boundary Walls and Street Trees covers the council side of this.

Crossover, footpath and kerb protected

Most Melbourne councils require an asset protection permit before demolition and record the condition of the footpath, kerb and crossover. Damage found at the end of the build becomes someone's bill, and if it was not recorded before demolition, it can end up as yours. Handover should include photos of the council assets in the condition the demolisher left them, and a clear note if the builder is taking over the asset protection permit or lodging a new one.

Temporary fencing and site security

An empty block with open access is a liability. Agree whether the demolisher's temporary site fencing stays until the builder's fencing goes up, who pays for any overlap, and who is responsible for the site in between. A gap of even a week can invite dumping on a cleared block.

Handover documents

This is the part that is easily forgotten and slow to recover later. Your builder, surveyor and insurer may ask for any of the following, so collect them before the demolisher leaves.

Written confirmation that electricity, gas and water have been abolished, not just disconnected, and that telecommunications have been removed. The abolishment step is covered in Power, Gas and Water: Why Abolishment Takes Longer Than You Think.

Where asbestos was removed, the waste disposal documentation showing it went to a licensed facility, and a clearance certificate from an independent assessor where one was required.

A copy of the demolition permit, and the final inspection or completion paperwork your building surveyor issues.

Disposal dockets and completion photographs of the cleared block, with the location of old service runs and any backfilled areas marked.

Put the checklist in the contract

The easiest way to make this work is to attach the builder's handover requirements to the demolition quote and ask the contractor to confirm each item as included or excluded. That turns a vague promise of a clear block into a defined result, and it gives you something to check against on the last day.

Our Knockdown-Rebuild Site Preparation service is built around this handover, working backwards from your builder's start date. If you would like a scope written against your builder's requirements anywhere across Melbourne, send us their site conditions and we will quote to them.